Resolution | - When using Fixed Order Cycles or Order Days in Week and ordering 2 or more times a week customer may run into a situation where the Order Cycle on the vendor does not match the actual number of days between orders
- This can cause a overstock or understock situation. For example, if ordering on Monday and Thursday and setting Vendor's order cycle to a '3' will give you one less day of inventory. Conversly, setting the Vendor Order Cycle to '4' gives one additional day of inventory
- The best way to manage the Vendor Order Cycle in this situation is to use the Calendar module. With the calendar module you can manage Order Cycle value by day of week
|
|
---|