Additional Information | - Unit Cost can be set up in Product Level or Performance level
- The Unit Cost data used for calculations may come from the Product-level or Performance-level field depending on the Use Performance Cost setting on the Performance tab of the Project Properties dialog box.
- Data can be entered for either the Case Cost (Product) or the Unit Cost (Product) field as each field is calculated from the other based on how many units fit into a case.
- Unit Cost (Performance) calculation is Cost Before Tax(Performance) / Case Total Number(Product)
- Data can be entered for either the Case Cost (Performance) or the Unit Cost (Performance) field as each field is calculated from the other based on how many units fit into a case.
|
|
---|